Classrooms work progress

Posted on: 17 August 2015
By:
No Comments »
Filed under: Classrooms

The external contractors report that they are a little behind overall with the programme of works for the rooms across the 4 major buildings. However it is looking likely that 7 classrooms will be handed over complete with new AV by the 31st August and a further 8 rooms by September 7th. The remaining rooms, mostly at Cavendish, are set to complete by the 21st September at the latest.