Progress with the classrooms project

Posted on: 8 April 2015
By:
No Comments »
Filed under: Classrooms

The design company working on the project, Rock Townsend, have now had an opportunity to tour all of the rooms identified by the Faculties. They are currently working with the outline ideas for each room that some Faculties have already provided. Early next week we are hoping to have similar outline ideas from the remaining Faculties.

Click to see the ideas that have come from MAD and those from FST.

The timeline for the project is challenging and looks as follows:

Engagement with Faculties March – April
Design /cost plan complete: 24 April, to allow your presentation to the Project Board
Tender pack completion: 24 April – 1 May
Tender: May (4 weeks)
Negotiate with possible contractors: end/May – mid June
Instruct Main contractor and AV specialist contractor: mid June
Construction: July/August
Completion: end of August