New Classrooms – updated programme of works
Posted on: 24 August 2015
By: saundeg
No Comments »
Filed under: Classrooms
Parkeray the main contractors delivering the New Classrooms changes have released an updated programme of work for each room with projected completion dates as below:
Regent RS2.51 07 September 2015
Regent RS3.54 07 September 2015
Harrow A7.01 10 September 2015
Harrow A7.02 10 September 2015
Harrow A7.03 11 September 2015
Harrow A7.04 11 September 2015
Cavendish C1.110 07 September 2015
Cavendish C2.04 14 September 2015
Cavendish C2.07 11 September 2015
Cavendish C2.11 11 September 2015
Cavendish C3.05 14 September 2015
Marylebone C1.76 15 September 2015
Marylebone C1.78 15 September 2015
Marylebone C1.81 16 September 2015
Marylebone C1.80 16 September 2015
Marylebone LA1.03 17 September 2015
Marylebone C1.79 17 September 2015
Marylebone C2.79 08 September 2015
Marylebone C2.80 08 September 2015
Marylebone C2.81 07 September 2015
Marylebone C2.82 07 September 2015
Marylebone M3.21 18 September 2015
Latest posts by saundeg (see all)
- What to do about students referred or deferred in modules no longer running - 13 September 2016
- Personal Tutoring Dashboard - 13 September 2016
- Sensus Access - 13 September 2016
Leave a Reply